Project record

MRL09-Y.N Hosakote to SH-03 via R.D Roppa,Dalavaihalli,Bheemanakunte,Thimmanahalli

PMGSY-III · package KN25157 · Pavagada block · Maintenance

Location
Pavagada block, Tumakuru district
Alignment drawn
244 m · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL09-Y.N Hosakote to SH-03 via R.D Roppa,Dalavaihalli,Bheemanakunte,Thimmanahalli

OMMAS lists PMGSY-III work KN25157 as “MRL09-Y.N Hosakote to SH-03 via R.D Roppa,Dalavaihalli,Bheemanakunte,Thimmanahalli”.

Road Name / Bridge Name: MRL09-Y.N Hosakote to SH-03 via R.D Roppa,Dalavaihalli,Bheemanakunte,Thimmanahalli

[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 6

VerifiedOfficial record

Project / work ID

KN25157

OMMAS package number KN25157.

VerifiedOfficial record

Responsible agency

DPIU Of Tumkur

The programme implementation unit is recorded as “DPIU Of Tumkur”.

Programme Implementation Unit: DPIU Of Tumkur

[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 6

VerifiedOfficial record

Contractor

H.NARAYANAPPA [21 Aug 2020], H.NARAYANAPPA

OMMAS lists the contractor for this work as “H.NARAYANAPPA [21 Aug 2020], H.NARAYANAPPA”.

Contractor Name: H.NARAYANAPPA [21 Aug 2020], H.NARAYANAPPA [21 Aug 2020]

[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 6

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹343.02 lakh

The sanction cost is recorded as 343.02 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹47.86 lakh

The “5 Years Maintenance Cost Due” column shows 47.86 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

30-09-2022

The completion date column reads “Financial: 24-05-2024/ Physical: 30-09-2022”; the physical completion date is 30-09-2022.

Completion Date: Financial: 24-05-2024/ Physical: 30-09-2022

[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 6

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

8.130 km

Road length 8.130 km; 8.130 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record