Project record
DandinaShivara - Y.T. road (T -18)
PMGSY-I · package KN2520 · Turuvekere block · Completed
- Location
- Turuvekere block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
DandinaShivara - Y.T. road (T -18)
OMMAS lists PMGSY-I work KN2520 as “DandinaShivara - Y.T. road (T -18)”.
Road Name / Bridge Name: DandinaShivara - Y.T. road (T -18)
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28
Project / work ID
KN2520
OMMAS package number KN2520.
Package No.: KN2520
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28
Contractor
C N SOMASHEKAR [15 Jun 2006], Shivananda
OMMAS lists the contractor for this work as “C N SOMASHEKAR [15 Jun 2006], Shivananda”.
Contractor Name: C N SOMASHEKAR [15 Jun 2006], Shivananda [23 Nov 2009]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹349.80 lakh
The sanction cost is recorded as 349.80 (₹ lakh).
Sanction Cost: 349.80
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28
Maintenance cost due
₹27.32 lakh
The “5 Years Maintenance Cost Due” column shows 27.32 (₹ lakh).
5 Years Maintenance Cost Due: 27.32
[9]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-01-2011
The completion date column reads “Financial: 19-06-2012/ Physical: 31-01-2011”; the physical completion date is 31-01-2011.
Completion Date: Financial: 19-06-2012/ Physical: 31-01-2011
[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
22.000 km
Road length 22.000 km; 22.150 km recorded as completed.
Road Length (Kms): 22.000
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 28