Project record
k.k.road - jakkenahalli.T-01
PMGSY-I · package KN2540 · Tumkur block · Completed
- Location
- Tumkur block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
k.k.road - jakkenahalli.T-01
OMMAS lists PMGSY-I work KN2540 as “k.k.road - jakkenahalli.T-01”.
Road Name / Bridge Name: k.k.road - jakkenahalli.T-01
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Project / work ID
KN2540
OMMAS package number KN2540.
Package No.: KN2540
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Contractor
H S Shanmukha
OMMAS lists the contractor for this work as “H S Shanmukha”.
Contractor Name: H S Shanmukha [16 Oct 2007]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹109.32 lakh
The sanction cost is recorded as 109.32 (₹ lakh).
Sanction Cost: 109.32
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Maintenance cost due
₹7.85 lakh
The “5 Years Maintenance Cost Due” column shows 7.85 (₹ lakh).
5 Years Maintenance Cost Due: 7.85
[9]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-01-2010
The completion date column reads “Financial: 23-06-2010/ Physical: 31-01-2010”; the physical completion date is 31-01-2010.
Completion Date: Financial: 23-06-2010/ Physical: 31-01-2010
[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
5.250 km
Road length 5.250 km; 5.250 km recorded as completed.
Road Length (Kms): 5.250
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26