Project record
lingapura - T-07
PMGSY-I · package KN2541 · Tumkur block · Completed
- Location
- Tumkur block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
lingapura - T-07
OMMAS lists PMGSY-I work KN2541 as “lingapura - T-07”.
Road Name / Bridge Name: lingapura - T-07
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Project / work ID
KN2541
OMMAS package number KN2541.
Package No.: KN2541
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Contractor
Guru and Co Tumkur
OMMAS lists the contractor for this work as “Guru and Co Tumkur”.
Contractor Name: Guru and Co Tumkur [07 Jul 2007]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹131.94 lakh
The sanction cost is recorded as 131.94 (₹ lakh).
Sanction Cost: 131.94
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Maintenance cost due
₹9.35 lakh
The “5 Years Maintenance Cost Due” column shows 9.35 (₹ lakh).
5 Years Maintenance Cost Due: 9.35
[9]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2009
The completion date column reads “Financial: 14-10-2010/ Physical: 31-03-2009”; the physical completion date is 31-03-2009.
Completion Date: Financial: 14-10-2010/ Physical: 31-03-2009
[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
6.250 km
Road length 6.250 km; 6.250 km recorded as completed.
Road Length (Kms): 6.250
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 26