Project record
Bydarahalli - T-01
PMGSY-I · package KN2557 · Tiptur block · Completed
- Location
- Tiptur block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Bydarahalli - T-01
OMMAS lists PMGSY-I work KN2557 as “Bydarahalli - T-01”.
Road Name / Bridge Name: Bydarahalli - T-01
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23
Project / work ID
KN2557
OMMAS package number KN2557.
Package No.: KN2557
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23
Contractor
M G SHIVASHANKARA SWAMY
OMMAS lists the contractor for this work as “M G SHIVASHANKARA SWAMY”.
Contractor Name: M G SHIVASHANKARA SWAMY [04 Jul 2008]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹228.48 lakh
The sanction cost is recorded as 228.48 (₹ lakh).
Sanction Cost: 228.48
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23
Maintenance cost due
₹18.25 lakh
The “5 Years Maintenance Cost Due” column shows 18.25 (₹ lakh).
5 Years Maintenance Cost Due: 18.25
[9]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-07-2011
The completion date column reads “Financial: 18-11-2011/ Physical: 31-07-2011”; the physical completion date is 31-07-2011.
Completion Date: Financial: 18-11-2011/ Physical: 31-07-2011
[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
9.990 km
Road length 9.990 km; 9.990 km recorded as completed.
Road Length (Kms): 9.990
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 23