Project record
Gollarahatti - T-06
PMGSY-I · package KN2581 · Sira block · Completed
- Location
- Sira block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Gollarahatti - T-06
OMMAS lists PMGSY-I work KN2581 as “Gollarahatti - T-06”.
Road Name / Bridge Name: Gollarahatti - T-06
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20
Project / work ID
KN2581
OMMAS package number KN2581.
Package No.: KN2581
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20
Contractor
A S R Constructions
OMMAS lists the contractor for this work as “A S R Constructions”.
Contractor Name: A S R Constructions [01 Oct 2009]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹152.56 lakh
The sanction cost is recorded as 152.56 (₹ lakh).
Sanction Cost: 152.56
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20
Maintenance cost due
₹10.90 lakh
The “5 Years Maintenance Cost Due” column shows 10.90 (₹ lakh).
5 Years Maintenance Cost Due: 10.90
[9]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-07-2011
The completion date column reads “Financial: 07-03-2012/ Physical: 31-07-2011”; the physical completion date is 31-07-2011.
Completion Date: Financial: 07-03-2012/ Physical: 31-07-2011
[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
5.340 km
Road length 5.340 km; 5.340 km recorded as completed.
Road Length (Kms): 5.340
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 20