Tender document — White Topping of Selected Roads under GoK Grants, Package-2 (BBMP, Project Central-8)

Bruhat Bengaluru Mahanagara Palike, via Karnataka Public Procurement Portal

Comprehensive Development of Selected Roads by Providing
White Topping Under GoK Grants Package - 2 Technical Bid
Tenderer Page 32 of 65 Executive Engineer,
PC-8, BBMP, Bengaluru
Conditions of Contract
A. General
1. Definitions
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of
Contract but keep their Defined Meanings. Bold Letters are used to identify Defined Terms.
Bill of Quantities means the Priced and Completed Bill of Quantities forming part of the
Tender.
Compensation Events are those defined in Clause 38 hereunder.
The Completion Date is the Date of Completion of the Works as certified by the Employer in
accordance with Sub Clause 46.1.
The Contract is the Contract between the Employer and the Contractor to execute, complete
and maintain the Works. It consists of the Documents listed in Clause 2.2 below.
The Contract Data defines the Documents and other Information, which comprise the
Contract.
The Contractor is a Person or Corporate Body whose Tender to carry out the Works has
been accepted by the Employer.
The Contractor's Tender is the Completed Tender Document submitted by the Contractor to
the Employer.
The Contract Price is the Price stated in the Letter of Acceptance and thereafter as adjusted
in accordance with the Provisions of the Contract.
Days are Calendar Days; Months are Calendar Months.
A Defect is any Part of the Works not completed in accordance with the Contract.
The Defects Liability Period is the Period named in the Contract Data and calculated from
the Completion Date.
The Employer is the Party who will employ the Contractor to carry out the Works.
Equipment is the Contractor's Machinery and Vehicles brought temporarily to the Site to
construct the Works.
The Initial Contract Price is the Contract Price listed in the Employer's Letter of Acceptance.
The Intended Completion Date is the Date on which it is intended that the Contractor shall
complete the Works. The Intended Completion Date is specified in the Contract Data. The
Intended Completion Date may be revised only by the Employer by issuing an Extension of
Time.
Materials are all Supplies, including Consumables, used by the Contractor for incorporation
in the Works.
Plant is any Integral Part of the Works which is to have a Mechanical, Electrical, Electronic or
Chemical or Biological Function.
The Site is the Area defined as such in the Contract Data.
Specification means the Specification of the Works included in the Contract and any
Modification or Addition made or approved by the Employer.
The Start Date is given in the Contract Data. It is the date when the Contractor shall
commence Execution of the Works. It does not necessarily coincide with any of the Site
Possession Dates.
A Subcontractor is a Person or Corporate Body who has a Contract with the Contractor to

Text as extracted by CivicProof (at ingest, or when the investigator fetched the record). Structured records (portal API responses) are shown as field: value lines.