Tender document — White Topping of Selected Roads under GoK Grants, Package-2 (BBMP, Project Central-8)

Bruhat Bengaluru Mahanagara Palike, via Karnataka Public Procurement Portal

Comprehensive Development of Selected Roads by Providing
White Topping Under GoK Grants Package - 2 Technical Bid
Tenderer Page 51 of 65 Executive Engineer,
PC-8, BBMP, Bengaluru
The Compensation, if any, shall be paid directly to the Department / Authority / Persons
concerned, by the Contractor at his own Cost.
34. The Contractor will take all Necessary Measures for the Safety of Workers during
Construction and provide, erect and maintain such Barricades, including Signs, Markings,
Flags and Lights, as necessary, all around the Excavation / Construction Area and at such
Intermediate Points, as directed by the Employer including the Proper Identification of the
Construction Areas. He shall be Responsible for all Damages and Accidents on account of
Construction and other Relevant Activities. Nothing shall be paid extra on account of above.
The Temporary Warning Signs / Lamps shall be installed at all Barricades during the Hours
of Darkness and kept lit there at all times during these hours and nothing shall be paid extra.
The above Provisions shall be followed strictly and at no time the Construction / Excavation
Areas are to be left Unbarricaded or without Red Lamps during the Hours of Darkness.
Failure to comply with the Requirements mentioned in the Preceding Paragraphs shall be
deemed to be a Breach of Contract on the Part of the Contractor for which the Contractor
shall be Liable to action under Relevant Clauses / Conditions of the Agreement.
In addition to other Actions being taken for such Breach of Contract, the Contractor shall be
liable to pay compensation @ Rs. 1000/- per Sqm of Area left Unbarricaded.
The Employer shall give Notice to the Contractor for such Barrication and the Contractor
shall comply with the same within one day of such Notice failing which he shall be liable to
pay the above Compensation and Actions for the said Breach of Contract. The Decision of the
Employer in respect of the above shall be final and binding. The Contractor shall be held fully
responsible for any lapses and consequent losses (Damages, Injuries, Death, etc.) in this
regard.
The Contractor shall use every Reasonable Means to prevent any of Roads, Bridges
communicating with or on the Routes to the Site from being damaged by any Traffic of the
Contractor or any of his Sub Contractors and in particular, shall select Routes and Vehicles to
avoid such Unnecessary Damages.
35 The Contractor shall assume all Liabilities, Financial or otherwise in connection with his
Contract and shall protect and save the Employer from any and all Damages and Claims that
may arise because of the Presence and Operations of others working on or near the Site. The
Contractor shall assume all Responsibilities for all Work not completed or accepted because
of the Presence and Operations of other Contractors or Piece Workers or of the Employer.

Text as extracted by CivicProof (at ingest, or when the investigator fetched the record). Structured records (portal API responses) are shown as field: value lines.