13. Insurance requirements are as under:
Sl. No. Type of Cover Minimum Cover for Insurance for 12
months
i. Works and of Plant and Materials The Sum stated in the Agreement plus
20%
ii. Loss or damage to equipment Full Replacement Cost
iii. Loss or damage to property of Third
Party
Full Replacement Cost
iv. Personal Injury or Death Insurance
a. for Third Party
b. for Contractor’s Employees or
Labour
Rs. 20.00 Lakh to cover 4 Persons @
Rs. 5.00 Lakh each.
In accordance with the Statutory
Requirements Applicable to Karnataka.
17. 26. The Intended Completion Date for the whole of the Works: 11 Months from the Start
Date including monsoon with the following Milestones.
Milestone Physical Work in
percentage (%) to be
completed (Cumulative)
Period from the Date of
Issue of Notice to proceed
with the Work
Milestone 1 25% 1/4th of Period of Completion
Milestone 2 50% 2/4th of Period of Completion
Milestone 3 75% 3/4th of Period of Completion
Milestone 4 100% Final Period of Completion
21. The Site Possession Date: Immediately after the Issue of Work Order.
21.1 The Contractor shall submit to the Employer for Approval a Program showing the
General Methods, Arrangements, Order and Timing for all the Activities in the Works:
within 10 days from the Date of Signing the Agreement.
25. The Methodology and Program of Construction: 10 Days from the Date of Entering
into Agreement.
25. The Schedule of Key and Critical Equipment to be deployed on the work as per Agreed
Program of Construction: 10 Days from the Date of Entering into Agreement.
31. The Defects Liability Period is 60 Months, which will run concurrently from the
Date of the Physical Completion of the Project and on issuance of Physical
Completion Certificate by the Competent Authority.