Tender document — White Topping of Selected Roads under GoK Grants, Package-2 (BBMP, Project Central-8)

Bruhat Bengaluru Mahanagara Palike, via Karnataka Public Procurement Portal

Comprehensive Development of Selected Roads by Providing
White Topping Under GoK Grants Package - 2 Technical Bid
Tenderer Page 9 of 65 Executive Engineer,
PC-8, BBMP, Bengaluru
3.4 To qualify for a Package of Contracts made up of this and other Contracts for which Tenders
are invited in this IFT, the Tenderer must demonstrate having Experience and Resources to
meet the Aggregate of the Qualifying Criteria for the Individual Contracts.
3.5 Sub Contractors’ Experience and Resources shall not be taken into account in determining
the Tenderers Compliance with the Qualifying Criteria.
3.6 Tenderers who meet the above specified minimum Qualifying Criteria, will only be qualified,
if their available Tender Capacity is more than the total Tender Value. The available Tender
Capacity will be calculated as under:
Assessed Available Tender Capacity = (A*N*1.5 – B)
Where
A = Maximum Value of Civil Engineering Works executed in any one year during the last
five years (updated to 2023 –24 Price Level) taking into account the completed as well
as works in progress.
N = Number of years prescribed for completion of the Works for which Tenders are
invited, i. e. 11 months.
B = Value, at 2023 – 24 Price Level, of existing commitments and on going works to be
completed during the next 11 months.
Note: The Statements showing the value of existing commitments and on going works as well as the
stipulated period of completion remaining for each of the works listed should be
countersigned by the Employer in Charge, not below the Rank of an Executive Engineer or
equivalent.
3.7 Even though the Tenderers meet the above Criteria, they are subject to be Disqualified if they
have
 made Misleading or False Representations in the Forms, Statements and Attachments
submitted in Proof of the Qualification Requirements; and / or
 record of Poor Performance such as Abandoning the Works, not properly Completing the
Contract, Inordinate Delays in Completion, Litigation History, or Financial Failures, etc.
and / or
 Participated in the Previous Tender for the Same Work and had quoted Unreasonably
High Tender Prices and could not furnish Rational Justification.
4. One Tender per Tenderer
4.1 Each Tenderer shall submit only one Tender for each Project. A Tenderer who submits or
participates in more than one Tender (other than as a Sub Contractor or in cases of
alternatives that have been permitted or requested) will cause all the Proposals with the
Tenderer’s Participation to be disqualified.
5. Cost of Tendering
5.1 The Tenderer shall bear all Costs associated with the Preparation and Submission of his
Tender, and the Employer will in no case be Responsible and Liable for those Costs.