Tender SURE Phase A roads — project status presentation (Feb 2021)

Bengaluru Smart City Limited (copy hosted by OpenCity.in)

P H A S E A
PA C K A G E 1
• Project Cost : 31.75 cr
• Agency : Yoga & Co
• Duration: 15 Months
• Work Order Date: 01.03.2019
• Site Handover Date:25.04.2021
• Police Permission: 25.10.2019
• Financial Progress: 26% (8.36Cr)