Dickenson Road Status of Work on LHS Utilities : Completed Footpath : In Progress Street Light : In Progress Landscape : Yet to Start Carriage Way : DBM 1000Mtr Completed Status of Work on RHS Utilities : Completed Footpath : In Progress Street Light : In Progress Landscape : Yet to Start Carriage Way : DBM 1000Mtr Completed Overall Physical Progress : 85% Project Overview • Length of Road : 1200.00 M • Dual Carriageway Width (m) : 8.0 - 11.0 • Type of Carriageway: Dual • Type of Pavement: Flexible • Parking Provision: LHS • Landscape Provision: Yes • Footpath Provision: Yes
Tender SURE Phase A roads — project status presentation (Feb 2021)
Bengaluru Smart City Limited (copy hosted by OpenCity.in)
Page 16 of 65