Tender SURE Phase A roads — project status presentation (Feb 2021)

Bengaluru Smart City Limited (copy hosted by OpenCity.in)

Cantonment Road 570.00Mtr
Status of Work on LHS (Ch. 0 to
250- 12.5 m, From Ch. 210 to
570 – 6.5 m)
Utilities : Completed
Footpath : Completed
Street Light : Completed
Landscape: Completed
DBM/BC : BC pending
Physical Progress: 90%
Status of Work on RHS (4.50
Mtr Wide)
Utilities : Completed
Footpath : Completed
Street Light : Completed
DBM/BC : : BC pending
Physical Progress : 90%
Overall Physical Progress : 90%
Project Overview
• Length of Road : 1140.00 M
• Carriageway Width : 6.0- 12.0
m
• Type of Carriageway: Dual
• Type of Pavement: Flexible
• Parking Provision: No
• Landscape Provision: Yes
• Footpath Provision: Yes