Tender SURE Phase A roads — project status presentation (Feb 2021)

Bengaluru Smart City Limited (copy hosted by OpenCity.in)

Jumma Masjid Road
Status of Work on LHS (5.00 Mtr
Wide)
Utilities : Completed
Footpath : Completed
Street Light : Pole Erection
pending
Landscape: Plantation yet to
start
DBM/BC : BC Pending
Physical Progress: 85%
Status of Work on RHS (5.00
Mtr Wide)
Utilities : Completed
Footpath : Completed
Street Light : Pole Erection
pending
DBM/BC : BC Pending
Physical Progress : 85%
Overall Physical Progress : 85%
Project Overview
• Length of Road : 175.00 M
• Carriageway Width : 5.0 m
• Type of Carriageway: Dual
• Type of Pavement: Flexible
• Parking Provision: Yes
• Landscape Provision: Partial
• Footpath Provision: Yes