Jumma Masjid Road Status of Work on LHS (5.00 Mtr Wide) Utilities : Completed Footpath : Completed Street Light : Pole Erection pending Landscape: Plantation yet to start DBM/BC : BC Pending Physical Progress: 85% Status of Work on RHS (5.00 Mtr Wide) Utilities : Completed Footpath : Completed Street Light : Pole Erection pending DBM/BC : BC Pending Physical Progress : 85% Overall Physical Progress : 85% Project Overview • Length of Road : 175.00 M • Carriageway Width : 5.0 m • Type of Carriageway: Dual • Type of Pavement: Flexible • Parking Provision: Yes • Landscape Provision: Partial • Footpath Provision: Yes
Tender SURE Phase A roads — project status presentation (Feb 2021)