Tender SURE Phase A roads — project status presentation (Feb 2021)

Bengaluru Smart City Limited (copy hosted by OpenCity.in)

BENGALURU SMART CITY LIMITED
PROJECT STATUS
Sl. No. Name of the Road/
Project ID Length in km DPR Cost (in Cr.)
Awarded
Amount
(in Cr.)
Physical
progress Financial progress
Status
Anticipated
Date of
Completion
(in % ) (in % ) ( in Cr.)
PHASE-A ROADS
1
Commercial Street-From Kamaraj road to Jumma Masjid road(Near
Bowring Hospital). 0.458
35.93 31.75
82%
22% 6.98
Work is in
Progress 19.07.2021
Kamraj Road from M.G.Road upto Commercial street and Upto St. Johns
Church road. 1.829 53% Work is in
Progress
2
Ulsoor Road from Dickenson road to kingston road. 0.585
29.27 26.08
79%
60% 15.55
Work is in
Progress 20.07.2021
Dickenson road-From M.G.road to Kamaraj road. 1.200 81% Work is in
Progress 30.07.2021
3
Infantry Road from Ali Asker road to safina Plaza complex (Main Guard
Cross Road). 1.647
53.26 47.71
90%
54% 25.90
Work is in
Progress 25.07.2021
Central Street from M.G.Road to Shivajinagar Bus Stand (TTMC) and Upto
Indian Express (Balekundri) Junction. 0.842 79% Work is in
Progress
Bowring Hospital Road - Main Guard Cross Road to HSIS Gosha Hospital. 0.836 60% Work is in
Progress
4
Millers Road from Chalukya Circle to Cantonment Via Queens Road. 1.305
39.98 35.47
55%
10% 3.58
Work is in
Progress
Raj Bhavan Road from Minsk Square to Basaveshwara Circle. 0.920 82% Work in
Progress. 17.07.2021
5
Mcgarth Road - From Brigade Road upto Richmond Road (Near Hosmat
Hospital). 0.460
27.25 26.58
100%
88% 23.29
Completed
Convent road- From Richmond road to Residency road. 0.422 100% Completed
Hayes road-From Richmond road to Residency road. 0.310 100% Completed
Wood Street - From Museum road to Richmond road. 0.280 100% Completed
Castle Street- From Museum road to Richmond road. 0.380 100% Completed
Tate Lane – From Richmond road to Castle street. 0.130 100% Completed
6
Kasturba road - from Siddalingaiah circle to Minsq Square via Queens
Statue (M.G.Road). 0.735
45.75 40.72
92%
59% 23.95
Work in
Progress. 17.07.2021
Queens road – from M.G.road to Cantonment railway station. 1.827 94% Work in
Progress. Completed
Coffee Board - from Thimmaih Circle to Balkundri Junction 0.350 5%\
7
Raja Ram Mohan Roy Road from Richmond Circle to Hudson Circle 1.000
39.97 35.41
100%
96% 34.02
Completed
Lavelle Road from M.G.Road to Richmond Circle. 1.376 100% Completed
Brigade Road from M.G.Road to War Memorial Junction. 0.320 100% Completed Completed