Implementation of Projects and Monitoring 55 The State Government replied (April 2025) that the diversion works could not be completed due to paucity of funds. However, the reply was silent regarding the audit observation on wastage of drinking water and non-feasibility of pumping drinking water from Bugudunahalli Tank to Amanikere Tank. 4.12 Parks and Public Spaces The projects under “Parks and Public Spaces” included developing green areas and parks, transforming open spaces with recreational avenues, waterfront development etc. The physical and financial progress of the projects taken up under ‘parks and public spaces’ as of June 2024 is given in Table 4.13. Table 4.13: Physical and financial progress under Parks and Public Spaces Sl. No Smart City Physical progress (in numbers) Financial progress (₹ in crore) Total Completed Ongoing Project Cost Expenditure 1 Belagavi 22 18 4 85.58 51.94 2 Bengaluru 2 2 0 43.07 43.07 3 Davanagere 4 4 0 13.35 13.35 4 Hubballi-Dharwad 13 12 1 266.13 198.66 5 Mangaluru 13 6 7 91.56 42.41 6 Shivamogga 14 13 1 154.86 152.27 7 Tumakuru 41 40 1 97.79 92.17 Grand Total 109 95 14 752.34 593.87 Source: Information furnished by Smart Cities Audit test checked 40 out of 109 projects taken up under “Parks and Public Spaces”. Major observations are detailed below: 4.12.1 Non-achievement of rejuvenation of Unkal lake HDSCL took up the project ‘Upgradation of Unkal lake including operation and maintenance’ in two phases to rejuvenate the deteriorated lake which had been a primary drinking water source for Hubballi city. The scope of Phase-I works included removing Water Hyacinth, installing aerators, trash barriers, bio frames, ecological floating beds, ecological bridge filter at the inlet of the lake and bioremediation. The scope of Phase-II included fencing of the lake, development of pathway/causeway along the edge of the lake, construction of gabion wall, development of existing bund, refurbishment of structures etc. Audit observed that the contractor stopped Phase I work in 2021 after achieving financial progress of ₹3.67 crore, while there was no physical progress in respect of Phase II work. Only an amount of ₹1.63 crore was paid (July 2021) to the contractor towards mobilisation advance under Phase II. HDSCL issued (February 2022) termination notice to the contractor implementing Phase I of the project. The PMC in its report (June 2022) also recommended foreclosure of the contract as the contractor had not completed the work as per the milestone design.
CAG Report No. 11 of 2025 — Implementation of Smart City Mission, Government of Karnataka
Comptroller and Auditor General of India
Page 75 of 110
Text as extracted by CivicProof (at ingest, or when the investigator fetched the record). Structured records (portal API responses) are shown as field: value lines.