Avenue Road Status of Work on LHS (Ch. 0 to 80- 11m, From Ch. 80 to 1020 – 7m) Utilities : Completed Footpath : Yet to start Street Light : Yet to start Carriage Way : PQC In progress Physical Progress: 60% Status of Work on RHS (Ch. 0 to 80- 11m, From Ch. 80 to 1020 – 7m) Utilities : Completed Footpath : In progress Street Light : Yet to start Carriage Way : PQC In progress Physical Progress : 60% Overall Physical Progress : 56% Project Overview • Length of Road : 1020.00 M • Carriageway Width : 5.50 m • Parking Provision: Partial • Landscape Provision: No • Footpath Provision: Yes
Tender SURE Phase A roads — project status presentation (Feb 2021)