Tender SURE Phase A roads — project status presentation (Feb 2021)

Bengaluru Smart City Limited (copy hosted by OpenCity.in)

Rhenius Street
Status of Work on LHS (Ch. 0
to 210- 6.5m, From Ch. 210 to
570 – 7.5m)
Utilities : Completed
Footpath : In progress
Street Light : Yet to start
Landscape: In progress
DBM/BC : Pending
Physical Progress: 65%
Status of Work on RHS (6.0
Mtr Wide)
Utilities : Completed
Footpath : Completed
Street Light : Pole foundation
completed
Landscape: Completed
DBM/BC : BC Pending
Physical Progress : 90%
Overall Physical Progress : 75%
Project Overview
• Length of Road : 570.00 M
• Carriageway Width : 6.0 m
• Parking Provision: Yes
• Landscape Provision: Yes
• Footpath Provision: Yes