Chapter-IV 26 that the CEOs were not available for most of the initial phases of implementation of scheme ranging from 26 months to five years which was in violation of the SCM guidelines and delayed the completion of projects. 4.3 Lack of Operational Independence Paragraph 4 of Annexure 5 of SCM guidelines specifies that the primary reason for creation of an SPV for SCM was to ensure operational independence and autonomy in decision making and mission implementation. To enable the same, SCM guidelines encourages the State Government and the ULBs to delegate: (i)Rights and obligations of the municipal council with respect to the Smart City project to the SPV, (ii) the decision-making powers available to the ULB to the Chief Executive Officer of the SPV, (iii) the approval or decision making powers available to the Municipal Administration department to the Board of Directors of the SPV and (iv) the matters that require the approval of the State Government to the State Level High Powered Steering Committee (HPSC) for Smart Cities. Audit scrutiny of the Memorandum of Association (MoA) and Articles of Association (AoA) of the seven SPVs, revealed that except for Bengaluru, no SPV was empowered to approve and sanction projects including technical appraisal as prescribed in the Mission guidelines. Except for Bengaluru, the MoA and AoA of other smart cities contained the clause ‘To get approval and sanction of projects’ instead of ‘Approve and sanction projects’ as provided in the model documents. Consequently, the full powers in respect of approval of tender/variations and extension of time for projects were vested with HPSC. Further, the prior approval of Technical Committee (TC), KUIDFC was to be obtained for approval of variations. State Government granted SPVs full powers in respect of extension of time and approval of variations only during December 2022, which was withdrawn during July 2023 indicating retaining of powers by the State Government instead of SPVs. The State Government replied (April 2025) that the State Technical Committee constituted at KUIDFC was scrutinising the DPRs and according approvals. The reply is not acceptable for the reason that the delegation of powers to technical committee was in contravention of the SCM guidelines. 4.4 Delay in awarding of projects As per the project implementation timeline provided in the MoHUA Annual Report, the award of works should be completed within 12 to 18 months of incorporation of the SPVs. However, Audit observed that SPVs could award only 45 out of 645 (seven per cent) projects within the stipulated timeline as detailed in Table 4.3.
CAG Report No. 11 of 2025 — Implementation of Smart City Mission, Government of Karnataka
Comptroller and Auditor General of India
Page 46 of 110
Text as extracted by CivicProof (at ingest, or when the investigator fetched the record). Structured records (portal API responses) are shown as field: value lines.