Chapter-IV 46 DWC37 pipes for carrying the electricity cables in the underground ducts incurring an expenditure of ₹15.70 crore38. Audit observed that the decision of laying of DWC pipes was taken without analysing its technical feasibility as detailed below: • Mangalore Electricity Supply Company (MESCOM) had suggested (January 2020) not to lay HT/LT cables through DWC pipes due to demerits such as poor heat dissipation, insufficient mechanical strength, chances of water accumulation in HT/LT chambers etc. • DSCL utilised single wall HDPE39 pipes as conduit material with benefits such as durability, easy handling and workability, high tensile strength etc., and thus offered enhanced protection to the electricity cables and was handy for carrying out repair works. • Even the Technical Committee, KUIDFC had recommended (May 2020) laying HDPE pipes in place of DWC pipes while approving variations for Smart Road packages. Thus, laying DWC pipes by TSCL, SSCL and HSCL without considering the inputs from the user departments and without conducting adequate technical investigations resulted in inadequate quality control for the expenditure incurred. The technical Committee, KUIDFC also failed to adopt a uniform and feasible stand while deciding the conduit material for electricity duct during the DPR approval stage as HDPE pipes were used in other Smart Cities. The reply furnished by the Government is silent on the above audit observation. 4.10.5 Non-utilisation of road constructed under the Mission MSCL undertook (March 2021) the construction of the connecting road from NH-66 near Jeppu to Morgan’s gate including construction of Road Under Bridge (RUB) to reduce the traffic congestion at Pump well circle which was the entry point to Mangaluru city from NH 66. The work included three parts as detailed below. • Four lanes 18 metre wide connecting road of length 485 metre from NH 66 to proposed RUB. • Four lanes RUB to Mangaluru junction and Central Railway Station40. • Four Lanes 18-metre-wide connecting road of length 650 metre from proposed RUB to Emphasis junction. The total project cost of the work was ₹ 49.95 crore including construction of Railway Under Bridge (RUB). Out of total project cost of ₹ 49.95 crore, an amount of ₹30.07 crore was transferred (August 2019 to March 2021) to Indian Railways for construction of RUB. The construction of the connecting roads at the cost of ₹17.06 crore, commenced during March 2021 and was originally scheduled for completion by March 2022. As of May 2024, the project is still 37 Double wall Corrugated. 38 HDSCL ₹8.81 crore, TSCL ₹3.27 crore and SSCL ₹3.62 crore. 39 High density Polyethylene. 40 The work was initially taken up by MCC and an amount of ₹13.99 lakh was deposited (June 2014) with Indian Railways.
CAG Report No. 11 of 2025 — Implementation of Smart City Mission, Government of Karnataka
Comptroller and Auditor General of India
Page 66 of 110
Text as extracted by CivicProof (at ingest, or when the investigator fetched the record). Structured records (portal API responses) are shown as field: value lines.