B. Time Control
25. Program
25.1 Within the Time stated in the Contract Data, the Contractor shall submit to the Employer for
Approval a Program showing the General Methods, Arrangements, Order and Timing for all
the Activities in the Works.
25.2 The Employer's Approval of the Program shall not alter the Contractor's Obligations. The
Contractor may revise the Program and submit it to the Employer again at any time. A
Revised Program is to show the Effect of Variations and Compensation Events.
26. Extension of the Intended Completion Date
26.1 The Employer shall extend the Intended Completion Date if a Compensation Event occurs or
a Variation is issued which makes it impossible for Completion to be achieved by the
Intended Completion Date.
26.2 The Employer shall decide whether and by how much to extend the Intended Completion
Date within 21 Days of the Contractor asking the Employer for a Decision upon the Effect of a
Compensation Event or Variation and submitting Full Supporting Information.
27. Delays ordered by the Employer
27.1 The Employer may instruct the Contractor to delay the Start or Progress of any Activity
within the Works.
28. Management Meetings
28.1 The Employer may require the Contractor to attend a Management Meeting. The Business of
a Management Meeting shall be to review the Progress Achieved and the Plans for Remaining
Work.
28.2 The Responsibility of the Parties for Actions to be taken is to be decided by the Employer
either at the Management Meeting or after the Management Meeting and stated in writing to
be distributed to all who attended the Meeting.
C. Quality Control
29. Identifying Defects
29.1 The Employer shall check the Contractor's Work and notify the Contractor of any Defects that
are found. Such Checking shall not affect the Contractor's Responsibilities. The Employer may
instruct the Contractor to search for a Defect and to uncover and test any Work that the
Employer considers may have a Defect.
30. Tests
30.1 If the Employer instructs the Contractor to carry out a Test not Specified in the Specification
to check whether any Work has a Defect and the Test shows that it does, the Contractor shall
pay for the Test and any Samples. If there is no Defect the Test shall be a Compensation
Event.