SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export)

NRIDA, Ministry of Rural Development (OMMAS citizen reports)

The quoted excerpt is highlighted below, exactly where it appears in the extracted text.

State: Karnataka District : Bangalore R Block : All Blocks Year : All Years Batch : All Batches Collaboration : All Collaborations Status : All Status Loan Number: Not Available Scheme : PMGSY 2 Sub Scheme : All Note : All Costs are in Lakhs and All Lengths are in Kms.

Sr.No.: 7; District Name: Bangalore R; Programme Implementation Unit: DPIU Of Bangalore r; Block Name: Hosakote
Package No.: KN02114; Sanctioned Year: 2013 - 2014; Work Type: ROAD; Connectivity (New / Upgrade): Upgarde
Road Name / Bridge Name: MRL2-Doddanalla To Mylapura NH-4 Via., Nidagatta
Name of Benefited Habitations: Doddanallala [ 305614], Nidagatta [ 782155]
Sanction Cost: 271.98; State Cost: 70.34; Road Length (Kms): 5.700; Bridge Length (Mtrs): 0.000
Road Length Completed Till Date: 5.700; Expenditure Till Date: 240.74; Stage of Progress: Maintenance; Collaboration: Regular PMGSY
Contractor Name: M N CHANDRASHEKARAIAH [28 Feb 2014]
5 Years Maintenance Cost Due: 16.67; Completion Date: Financial: 11-08-2016/ Physical: 31-03-2015

Sr.No.: 8; District Name: Bangalore R; Programme Implementation Unit: DPIU Of Bangalore r; Block Name: Hosakote
Package No.: KN02115; Sanctioned Year: 2013 - 2014; Work Type: ROAD; Connectivity (New / Upgrade): Upgarde
Road Name / Bridge Name: MRL3-Ajjagondanahally to Muthsandra MDR Via., Gulakaipura
Name of Benefited Habitations: Ajjagondanhalli [ 20224], Gulakaipura [ 382700], Muthasandra [ 734545]
Sanction Cost: 234.46; State Cost: 59.94; Road Length (Kms): 5.980; Bridge Length (Mtrs): 0.000
Road Length Completed Till Date: 5.980; Expenditure Till Date: 200.94; Stage of Progress: Maintenance; Collaboration: Regular PMGSY
Contractor Name: M N CHANDRASHEKARAIAH [28 Feb 2014]
5 Years Maintenance Cost Due: 17.48; Completion Date: Financial: 06-02-2017/ Physical: 31-03-2015

Sr.No.: 9; District Name: Bangalore R; Programme Implementation Unit: DPIU Of Bangalore r; Block Name: Hosakote
Package No.: KN02116; Sanctioned Year: 2013 - 2014; Work Type: ROAD; Connectivity (New / Upgrade): Upgarde
Road Name / Bridge Name: MRL1-Balakune To Thavarekere NH-4 Via., Manchappnahally, Kalappnahally
Name of Benefited Habitations: Balanakunte [ 173469], Kalappanahalli [ 487294], Manchappanahalli [ 667533]
Sanction Cost: 188.77; State Cost: 48.31; Road Length (Kms): 4.940; Bridge Length (Mtrs): 0.000
Road Length Completed Till Date: 4.940; Expenditure Till Date: 182.77; Stage of Progress: Maintenance; Collaboration: Regular PMGSY
Contractor Name: M N CHANDRASHEKARAIAH [28 Feb 2014]
5 Years Maintenance Cost Due: 14.44; Completion Date: Financial: 11-08-2016/ Physical: 31-03-2015

Sr.No.: 10; District Name: Bangalore R; Programme Implementation Unit: DPIU Of Bangalore r; Block Name: Nelamangala
Package No.: KN02117; Sanctioned Year: 2013 - 2014; Work Type: ROAD; Connectivity (New / Upgrade): Upgarde
Road Name / Bridge Name: MRL3 - NH-04 To Thyamagondnhalli
Name of Benefited Habitations: Biragondanahally [ 166427], C T Palya [ 188144], Hosahalli [ 426048]
Sanction Cost: 153.15; State Cost: 39.43; Road Length (Kms): 5.172; Bridge Length (Mtrs): 0.000
Road Length Completed Till Date: 5.172; Expenditure Till Date: 187.52; Stage of Progress: Maintenance; Collaboration: Regular PMGSY
Contractor Name: M.G.Hanumantharaju [28 Feb 2014], S V T CONSTRUCTION [03 Mar 2018]
5 Years Maintenance Cost Due: 15.12; Completion Date: Financial: 14-11-2016/ Physical: 22-12-2015

Sr.No.: 11; District Name: Bangalore R; Programme Implementation Unit: DPIU Of Bangalore r; Block Name: Nelamangala
Package No.: KN02118; Sanctioned Year: 2013 - 2014; Work Type: ROAD; Connectivity (New / Upgrade): Upgarde
Road Name / Bridge Name: MRL5-Arebommanahalli to Byadrahalli Colony
Name of Benefited Habitations: Anandhnagar [ 36293], Aralasandra [ 43547], Arebommanahalli [ 44922], Arebommanahalli Colony [ 44923], Byadarahalli Colony [ 187477], Govindhapura [ 378532], Halkuru [ 394154], Thimmasandra [ 1050588]
Sanction Cost: 268.51; State Cost: 69.12; Road Length (Kms): 8.230; Bridge Length (Mtrs): 0.000
Road Length Completed Till Date: 8.230; Expenditure Till Date: 314.17; Stage of Progress: Maintenance; Collaboration: Regular PMGSY
Contractor Name: M.G.Hanumantharaju [28 Feb 2014], S V T CONSTRUCTION [03 Mar 2018]
5 Years Maintenance Cost Due: 24.07; Completion Date: Financial: 14-11-2016/ Physical: 06-04-2015

Sr.No.: 12; District Name: Bangalore R; Programme Implementation Unit: DPIU Of Bangalore r; Block Name: Nelamangala
Package No.: KN02119; Sanctioned Year: 2013 - 2014; Work Type: ROAD; Connectivity (New / Upgrade): Upgarde
Road Name / Bridge Name: MRL2-Baradi to T-Begur
Name of Benefited Habitations: Bardi [ 101315], Byranahalli [ 187824], Varadanaikanahalli [ 1088508]
Sanction Cost: 148.99; State Cost: 38.36; Road Length (Kms): 4.550; Bridge Length (Mtrs): 0.000
Road Length Completed Till Date: 4.550; Expenditure Till Date: 187.49; Stage of Progress: Maintenance; Collaboration: Regular PMGSY
Contractor Name: M.G.Hanumantharaju [28 Feb 2014], S V T CONSTRUCTION [03 Mar 2018]
5 Years Maintenance Cost Due: 13.30; Completion Date: Financial: 14-11-2016/ Physical: 25-11-2015