no other funds shall be credited to the account nor shall the account be
used other than for defraying admissible administrative, travel and quality
monitoring expenses.
(ix) The releases of administrative and travel expenses shall be dependent
on:
(a) continued updating of OMMAS modules
(b) appropriate dedication of the PIU and its clear linkage to the
SRRDA; and
(c) adequate institutional mechanism at the SRRDA level including
nodal IT officer, State Quality Coordinator, Financial Controller
and Empowered Officer.
(#Substituted vide MoRD letter No. P-17025/2/2008-RC dated 26th June, 2008)
12.3 No Agency charges will be admissible for road works taken up under 29
this Programme. In case Executing Agencies levy charges in any form, such as
Centage charges etc., it would have to be borne by the State Government.
13. EXECUTION OF WORKS
13.1 The relevant projects would be executed by the PIUs and completed within a
period of 9 months from the date of issue of the Work order. A Work Programme shall
be obtained from the contractor for each work and approved by the PIU. Payment
shall be made only after the approval of the work programme, deployment by the
Contractor of the requisite number of engineers and setting up of the Quality Control
Laboratory at site. In this connection, it is clarified that:
(i) The period of 9 months shall comprise 9 working months. In case the
period for execution is likely to be adversely affected by monsoon or other
seasonal factors, the time period for execution may be suitably determined
while approving the work programme, but shall not exceed 12 calendar
Pradhan Mantri Gram Sadak Yojana